The Harlesden Town Team are holding another meeting to discuss the Town Centre upgrade at the Salvation Army Building in Manor Park Road tonight. As so often, it coincides with another meeting I have to go to, so I won't be there, but I thought it might be of interest to see a timetable for the project, which is as follows:
June 2011: Station Road consultation complete
July 2011: Main scheme preliminary design completed
Sept 2011: Station Road streetworks begin
Sept 2011 Main scheme consultation
Oct 2011: Main scheme detailed design begins
Nov 2011: Scheme approval
Dec 2011: Station Road works completed
Jan 2012: Main scheme detailed design completed
Sept 2012: Main Scheme streetworks commence
April 2013: Main scheme streetworks complete