The Harlesden Town Team are holding another meeting to discuss the Town Centre upgrade at the Salvation Army Building in Manor Park Road tonight.  As so often, it coincides with another meeting I have to go to, so I won't be there, but I thought it might be of interest to see a timetable for the project, which is as follows:

June 2011: Station Road consultation complete


July 2011: Main scheme preliminary design completed

Sept 2011: Station Road streetworks begin

Sept 2011 Main scheme consultation

Oct 2011: Main scheme detailed design begins

Nov 2011: Scheme approval

Dec 2011: Station Road works completed

Jan 2012: Main scheme detailed design completed

Sept 2012: Main Scheme streetworks commence

April 2013: Main scheme streetworks complete